Wade Avenue Bridge - Capital Project

Capital Boulevard

Wake County, NC


North Carolina Department of Transportation

August 2016 - September 2019

$36 million

BACK TO ALL PROJECTS

Overview

Zachry Construction Corporation was awarded the Wake County bid-build project from the North Carolina Department of Transportation. The 0.82 mile project consists of grading, drainage, paving, signing, signals and structures replacement of Bridge #227 on US-70/US-401/NC50 over Peace Street and the Wade Avenue Bridge #213 on US-70/NC-50 over US-401.

The Wade Avenue Bridge was completed and opened to traffic in April 2019.

The opening of Ramp C to Peace Street shifted traffic onto Peace Street in May 2019, which was part of Phase I. Currently Stage II of the Peace Street Bridge is under construction and scheduled for completion in September 2019.

 

Project Elements

  • .82 Mile
  • Bridges
  • Drainage
  • Grading
  • Signals
  • Signing