I-40/ SR 3015 AIRPORT BOULEVARD INTERCHANGE

MORRISVILLE, NC

I-40/ SR 3015 AIRPORT BOULEVARD INTERCHANGE

Overview

In November 2019, ZCC was awarded a $35 million contract with the North Carolina Department of Transportation to enhance the Interstate 40 and Airport Boulevard Interchange in Morrisville. The Zachry crew began work in March 2020 and expect to finish in March 2025. The bulk of the work will be replacing the current single bridge with a Diverging Diamond Interchange (DDI) and adding auxiliary lanes to I-40 in both directions. 

Client:

NORTH CAROLINA DEPARTMENT OF TRANSPORTATION

Start Date:

March 2020

End Date:

March 2025

Contract Amount:

$35 MILLION