WHITE OAK BAYOU SEGMENT 105

HARRIS COUNTY, TX

WHITE OAK BAYOU SEGMENT 105

Overview

Segment 105 runs 7.8 miles along White Oak Bayou from 1960 to Hollister Rd. and is comprised of replacing drainage, reshaping, and protecting slopes from erosion by rock and concrete placement, and constructing trails for the community to use for recreation.

Client:

HARRIS COUNTY FLOOD CONTROL DISTRICT

Start Date:

December 2022

End Date:

August 2024

Contract Amount:

$27 MILLION